In August 2011 a Yorkshire brewer had a nasty surprise when an overdue inspection revealed ravaging corrosion had rendered the 46m stack unsafe. Bailey International designed, organised the manufacture and installed the new 27.5m replacement within 5 weeks of the order, thus minimising the total outage and lost production. Using a twin crane arrangement Bailey engineers placed the new unit on the existing foundation bolts with uncanny accuracy. The engineers were duly rewarded with a drop of good Yorkshire beer.

 